If you need to plant 300, 3-gallon plants and your crew plants an average of 10 plants per hour, how many total hours of labor is necessary?

Gain confidence in setting landscape plants with our quiz. Study with comprehensive questions that offer explanations and helpful hints. Prepare effectively for your exam today!

Multiple Choice

If you need to plant 300, 3-gallon plants and your crew plants an average of 10 plants per hour, how many total hours of labor is necessary?

Explanation:
To determine the total hours of labor necessary to plant 300, 3-gallon plants at a rate of 10 plants per hour, you can follow a straightforward calculation. The first step is to divide the total number of plants by the number of plants your crew can plant in one hour. In this scenario, you have 300 plants to plant, and the crew can plant 10 plants each hour. So, you perform the calculation: 300 plants ÷ 10 plants/hour = 30 hours. This result indicates that it will take 30 hours of labor to plant all 300 plants, which confirms that the total labor requirement aligns perfectly with this calculation. Therefore, 30 hours is indeed the correct answer for this scenario.

To determine the total hours of labor necessary to plant 300, 3-gallon plants at a rate of 10 plants per hour, you can follow a straightforward calculation. The first step is to divide the total number of plants by the number of plants your crew can plant in one hour.

In this scenario, you have 300 plants to plant, and the crew can plant 10 plants each hour.

So, you perform the calculation:

300 plants ÷ 10 plants/hour = 30 hours.

This result indicates that it will take 30 hours of labor to plant all 300 plants, which confirms that the total labor requirement aligns perfectly with this calculation. Therefore, 30 hours is indeed the correct answer for this scenario.